Charbonneau Utility Repair: Old Farm Road Phase I

Bid/RFP Status: 
Awarded
Bid/RFP Due Date: 
Thursday, March 11, 2021 - 2:00pm
Quest CDN Reference Number: 
7575890

The project consists of furnishing all materials, labor, equipment, and supervision for the open trench replacement of approximately 1500 lineal feet of storm pipe, between 4” and 36” in diameter, cure in place installation of approximately 2300 lineal feet of storm pipe, between 8” and 12” in diameter, replacement of approximately 900 lineal feet of water pipe, between 6” and 8” in diameter, replacement and restoration of water, sanitary, and storm appurtenances, such as manholes, catch basins, service laterals, fittings, valves, etc., trench resurfacing, bypass pumping, pipe and manhole abandonment, and curb, sidewalk, driveway, and landscape restoration and performance of such additional and incidental work as called for by the Specifications and Contract Documents.

Bid Results:  

  • Braun Construction - $1,474,871.50 
  • Emery & Sons Construction - $1,493,433.00
  • Landis & Landis - $1,566,520.00
  • M.L. Houck Construction - $1,614,988.90
  • Canby Excavating - $1,632,615.00
  • K & E Excavating, Inc. - $1,750,556.00
  • JWF General Contractors - $2,456,000.00